PASSPORT OF THE INVESTMENT PROJECT No. 1

1

Project name

LLC "Hunarmand"

2

Purpose of the project

Construction of a small hydroelectric power station "Khrasmoni" with a capacity of 400 kW.

3

Brief description of the project

The goal of this project is to provide the school, existing infrastructures and part of the population with electricity in the winter, as well as to process the surplus of agricultural products of farmers and the population.

Territory project implementation

Muminabad region, Khatlon region.

5

 branch

energetics

6

The main components of the construction of objects, the main and additional cost of the project

 

7

Having a business plan

Business plan according to the international standard

8

Project performance indicators:

net present value (NPV)
internal rate of return (IRR)
discounted payback period (DPP)

4 years

9

Areas of use of the main investments

The funds will be used to provide the school, existing infrastructures and part of the population with electricity in the winter.

10

Number of jobs created by the project

20 per

11

Estimated project duration

4 years

12

The total cost of the project

580 000 usd.

PASSPORT OF THE INVESTMENT PROJECT No. 2

1

 Project name

Small hydroelectric power plant project "DUOB"

2

Objective of the project

The proposed construction site for the “Duob” SHPP is located in the village of Margak, at a distance of 9 km north of the regional center of Muminabad. The project provides for power supply to the villages of Margak and Sadbargoh. The villages of Margak and Sadbargoh belong to the rural jamoat of Kulchashma, they consist of 200 households with a total population of 1450 people.

3

Brief description of the project

Construction of small hydroelectric power station "DUOB

4

Territory project implementation

Muminabad district. Khatlon region,

5

 branch

energetics

6

The main components of the construction of objects, the main and additional cost of the project

 

7

Having a business plan

Business plan developed

8

Project performance indicators:

net present value (NPV)
internal rate of return (IRR)
discounted payback period (DPP)

2 year

9

Areas of use of the main investments

The funds will be used for the construction of the small HPP DUOB

10

Number of jobs created by the project

10 per

11

Estimated project duration

4-5 per.

12

The total cost of the project

180 000 usd.

PASSPORT OF THE INVESTMENT PROJECT No. 3

1

Project name

Акционерное общество «Р. Мирзоев»

2

Objective of the project

The main goal of the project is the construction of a small hydroelectric power station on the Siyokhob river in the Muminaba district of the Khatlon region.

3

Brief description of the project

Construction of a small hydroelectric power station on the Siyokhob river

4

 Territory project implementation

Muminabad region, Khatlon region.

5

branch

energetics

6

The main components of the construction of objects, the main and additional cost of the project

For the construction of a hydroelectric power station on the Siyokhob River, it is necessary to purchase equipment for a hydroelectric unit, pipelines, transformers and other technical inventory. In case of commissioning of this small hydroelectric power station, the power supply of the population of the Muminabad region will improve.

7

Having a business plan

Business plan developed

8

Project performance indicators:

net present value (NPV)
internal rate of return (IRR)
discounted payback period (DPP)

2 year

9

Areas of use of the main investments

For the construction of a hydroelectric power station on the Siyokhob River, it is necessary to purchase equipment for a hydroelectric unit, pipelines, transformers and other technical inventory.

10

Number of jobs created by the project

12-16 per.

11

Estimated project duration

3 year

12

The total cost of the project

160070 usd